Type of work:waste management system construction
Start of work: | 17.12.2018. |
Completion deadline: | 20.12.2020. |
A few sentences about the project:
Our company carries out the investment in a consortium with MENTO Kft. The following main technical contents will be implemented:
- Szeged Sándorfalvi road waste pre-treatment plant construction (28,000 m2), construction of a new waste sorting hall (5,000 m2) with waste sorting technology, construction of a new bale and tool storage and social building
- Expansion of Szeged Sándorfalvi road landfill Phase 1 (2 ha)
- Expansion of the Szeged, Sándorfalvi road waste sorting plant
- Construction of the leachate treatment plant of the Regional Landfill in Sándorfalvi út, Szeged, with related infrastructure
- Construction of Szeged-Szőreg waste yard
- Disposal of waste collection islands